Horizontal Baler Replacement at Distribution Centre
A 28,000 lb horizontal baler was removed and replaced inside a high-volume distribution warehouse in Brampton. The project required careful planning to keep operations moving while installing the new unit in a single day.
28,000 Lbs
Weight Relocated
1 Day
Timeline
Project Details
Client Industry
Recycling & Waste Management
Equipment Weight
28,000 Lbs
Services Provided
Location
Special Equipment
Versa-Lift 40/60 , Hyster 15,000 Lbs Capacity Forklift, Machine Moving Dollies
Completed Date
March 2026
Project Overview
A major distribution warehouse in Brampton, Ontario required the replacement of an aging horizontal baler used to compress large volumes of cardboard generated from daily shipping operations. Because the facility processes significant packaging waste throughout the day, extended downtime was not an option.
The new baler arrived on site while the facility remained fully active. Our team was tasked with removing the existing unit and installing the replacement machine while keeping disruption to warehouse operations as minimal as possible.
The project required coordinated movement of both machines through an internal ramp area, carefully lowering the old unit and pushing the new 28,000-lb baler into position within the same working window.
To meet the tight timeline, Solid Hook deployed additional crew members and specialized moving equipment to complete the entire replacement safely within a single day.
The Challenge
• High-volume distribution facility generating constant cardboard waste • Limited shutdown window for replacing critical equipment • Heavy 28,000 lb horizontal baler located inside an active warehouse • Machines had to be moved up and down a ramp within the facility • Coordinating removal and installation within the same operational shift
Our Solution
• Deployed additional manpower to accelerate removal and installation • Used forklifts and controlled pushing techniques to manage ramp movement • Carefully extracted the old baler while protecting surrounding warehouse infrastructure • Positioned and installed the new baler in the same footprint • Completed the replacement within a single day to keep warehouse operations moving
Results
The existing baler was safely removed and the 28,000 lb replacement unit installed within the same day. By coordinating manpower and equipment, the Solid Hook team minimized operational disruption for the busy distribution facility, allowing the client to resume full waste-processing capacity immediately.