CNC Bridge Saw Container Extraction Without Dock Access
Unloading and placing a brand-new CNC stone bridge saw delivered in a shipping container at a customer facility without dock access, using staged height matching and controlled rigging sequencing.
20,000+ lbs
Weight Relocated
1 Day
Timeline
Project Details
Client Industry
Stone Fabrication
Equipment Weight
20,000 lbs
Services Provided
Location
Special Equipment
Landoll trailer, dock leveler, industrial machinery dollies, Versa-Lift 25/35
Completed Date
January 2026
Project Overview
Solid Hook was contracted to unload and position a newly delivered CNC stone bridge saw that arrived inside a shipping container at a customer facility without dock infrastructure.
Because the site did not have loading dock access, the machine could not be removed directly to grade. A staged trailer-based setup was required to match elevation and allow controlled extraction from the container before transferring the unit for final placement inside the facility.
The Challenge
-
-
No loading dock at delivery site
-
Machine delivered inside a shipping container
-
Elevation mismatch
-
Limited staging space outside facility
-
Need for controlled extraction to prevent load shift
Without dock access, direct forklift removal was not possible. The machine required a transitional setup to safely move from container to ground without instability.
-
Our Solution
-
-
Positioned a Landoll trailer with dock leveler to match container height
-
Installed machinery dollies under one end to enable controlled horizontal extraction
-
Used forklift-assisted pull-out sequencing from container to trailer platform
-
Transferred unit to ground using Versa-Lift 25/35
-
Positioned and aligned the bridge saw inside the facility to layout specification
This multi-stage transfer allowed safe container extraction, stable ground transition, and precision placement inside the shop.
-
Results
The CNC stone bridge saw was successfully extracted from the container and placed inside the facility without dock access.
Height matching using the Landoll setup ensured stable transfer from container to transitional platform. The Versa-Lift provided controlled offloading to grade, and final positioning inside the facility was completed without instability or surface damage.
The machine was safely staged and aligned, ready for integration into production.
20,000+ lbs
Weight Relocated
1 Day
Timeline